Various Work In Progress

We believe its important to see what goes into a loft as well as the finished product

Week 1

Installation of steel beams and structural floor

Week 2

Forming of dormers, internal walls and first fix plumbing and electrics

Week 3

Exterior roofing, insulating and plaster boarding.

Week 4

Plastering, second fix carpentry, electircs and plumbing.